BULKS

First ore goes to La Parrilla plant

Commissioning of new large-scale concentrator plant due in July

Staff reporter

This article is 6 years old. Images might not display.

Plant construction was completed in April, with the conveyors, pumps, thickener, two mills and two jigs commissioned over the past month.
 
W Resources said the plant took ore crushed to less than 10mm and increased the grade to be fed to the concentrator plant, achieving high tungsten and tin metal recoveries.
 
Chairman Michael Masterman pointed out the commissioning of the plant had not merely been a turn of a key process. 
 
"In the jig and mill plant alone there are two jigs, two roll mills, a thickener, reject disposal system, ten screens and feeders, nine conveyors, five pumps, and over 50 motors which need to be started, aligned and tied into an integrated control system," he said.
 
For now, the jigged mine feed will be fed through the existing concentrator plant, with the new large-scale concentrator plant still being built. Construction is expected to be completed in June, with commissioning due to take place in July.
 
Masterman said La Parrilla was on track to ramp-up to design production capacity of 200 tonnes per month by the end of 2019.
 
W Resources shares (AIM:WRES) rose 2.36% Tuesday to 0.46p (US0.58c), down from 0.54p at the start of January.
 

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Leadership Insights 2025

Leadership Insights reveals key trends in priority mining issues through interviews with 15+ top mining company executives and an industrywide survey.

editions

Mining IQ Risk Analytics

Risk Analytics offers interactive access to World Risk Insight data, allowing you to customise risk views, benchmark jurisdictions, explore data behind scores and read expert commentary to guide your decision-making.

editions

Project Pipeline Index 2025

View our 50 top mining projects, handpicked using a unique, objective selection process from an expanded database of 600+ global assets.