EXPLORATION & DEVELOPMENT

Leagold FS to take Los Filos to 350,000oz/y

Leagold Mining (TSX:LMC) has reported an expansion feasibility study for its Los Filos mine in Guerrero, Mexico, that incorporates the potential for development of the Bermejal underground mine, enlarging the Los Filos openpit mine, re-phasing of the Bermejal openpit into two distinct pits, and the construction of a carbon-in-leach (CIL) processing facility to complement the existing heap leach facilities.

Staff Reporter
 Leagold publishes expansion FS for Los Filos

Leagold publishes expansion FS for Los Filos

The study detailed the development of the Bermejal underground mine and new 4,000 tonne per day CIL plant at a capital cost of $180 million, yielding an after tax net present value of $565 million at a 5% discount rate and after tax internal rate of return of 87%.

The expansion will increase average annual production to 350,000oz of gold for 10 years at an all-in sustaining cost of US$759/oz from proven and probable mineral reserves of 111.3 million tonnes grading 1.23 grams a tonne containing 4.5Moz Au. The current Los Filos operation produced 195,362oz Au in 2018 at an AISC of around $1,000/oz.

"The study identifies a new operating strategy which includes three large open pits, two high-grade underground mines, the addition of a CIL plant to process the higher-grade ore, and the continued heap leaching of the lower-grade open pit ore," said CEO Neil Woodyer.

Leagold acquired Los Filos in April 2017 from Goldcorp and has since then carried out extensive exploration for both openpit and underground deposits, developed a 1,330m ramp to access the ore body at Bermejal underground, completed the Bermejal underground mine design, completed comprehensive metallurgical test work on all of the mineral deposits to support the CIL plant design, and learned a lot from current operations.

Its work investment to date is about $30 million.

The pre-commercial development phase for Bermejal underground extends to the third quarter of 2020.

The construction of the CIL plant will take 18 months, with commissioning and ramp-up to occur in the third quarter of 2020.

Expansion of openpit mining operations, with pre-stripping at Guadalupe and a pushback at Los Filos, is scheduled for 2020. The pushback to expand the Bermejal openpit is scheduled for 2021.

 

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.