PEA puts return above 100% for Azarga's Gas Hills uranium project

Satellite to Dewey Burdock

 Azarga Uranium’s Gas Hills project is in Wyoming where there is a history of uranium production

Azarga Uranium’s Gas Hills project is in Wyoming where there is a history of uranium production

The study put initial capex at US$26 million and estimated a post-tax IRR of 101% and NVP8 of $102.6 million.

It used a base case uranium price of $55 per pound and estimated pre-tax production costs of $28.20/lb.

The uranium spot price is currently about $32/lb.

Using a $35/lb uranium price, the PEA put pre-tax NPV at $34.9 million and IRR at 44%.

The study was based on a March resource update, which increased Gas Hills' measured and indicated resource by 128% to 10.77 million pounds U3O8 and put the M&I ISR resources at 7.7Mlb.

The PEA envisaged Gas Hills as a satellite development with final processing done at a facility to be constructed at Azarga's Dewey Burdock project across the border in South Dakota.

President and CEO Blake Steele said Wyoming had a long history of successful ISR operations.

"The PEA results further validate our company's strategy of developing low-cost ISR projects as we continue to progress our flagship Dewey Burdock project towards construction," he said.

"With uranium markets in a structural deficit, Azarga Uranium is exceptionally well positioned to capitalise on the anticipated recovery in the uranium price through its two tier one development-stage ISR uranium projects in the USA."

Gas Hills was forecast to produce a total of 6.5 million pounds of U3O8 over seven years, with steady state production of 1Mlb/year.

Dewey Burdock was expected to produce 14.3Mlb over 16 years according to a 2020 PEA.

Azarga had raised C$6 million in December at 20c per unit to advance its projects, repay loans and for general working capital.

Its shares (TSX: AZZ) have spanned C15.5-36c over the past year and closed unchanged at 25.5c yesterday, capitalising it at $59.6 million (US$48 million).

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.