Minera touts Cerro de Oro PEA as 'game changer'

The PEA includes an after-tax IRR of 111% and NPV5% of US$150.5 million

The average annual gold production is projected to be about 60,000oz to 70,000oz in years one through four, with an 8.2 year mine life.

The average annual gold production is projected to be about 60,000oz to 70,000oz in years one through four, with an 8.2 year mine life.

The PEA sees an after-tax NPV5% of US$150.5 million, pre-production capital costs of $28.1 million, and a payback period of 11 months, the company said.

"Leaning on our team's collective experience in mine building in Mexico with capital and operating costs informed by the recent construction and ramp up of the Santana gold mine, the Cerro do Oro PEA is a game changer for Minera as we strive to reach our initial target of a +100,000 ounce/year gold producer," Ramshaw said.

The average annual gold production is projected to be about 60,000oz to 70,000oz in years one through four, with an 8.2 year mine life.

The LOM all-in sustaining cost is set at $873/oz - averaging $763/oz in the first four years.

The Mexico-focused company produced its first gold in October 2021. Its portfolio includes the Santana open-pit, heap-leach mine in Sonora, which is going through an operational ramp-up, and the La Fortuna open pit project in Durango - along with Cerro do Oro in Zacatecas.

Minera's share price climbed 13% day on day to more than a three-month high of C$0.54 (US$0.40) on 4 October. The company has a market capitalisation of C$242.05 million.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.