Araguaia FS outlines US$56M annual cash flow

Horizonte says US$443 million, 14,500tpa, Brazil nickel project has strong numbers

Hot stuff: Horizonte has underlined the possible doubling of production at Araguaia once it is built, through installation of another RKEF process line

Hot stuff: Horizonte has underlined the possible doubling of production at Araguaia once it is built, through installation of another RKEF process line

In the project's newly released feasibility study, Horizonte outlines a 14,500-tonne-per-annum average production at a cash cost of $8,193 per tonne. Nickel has hit a poor patch in recent months, sitting...

Start a free trial to continue reading this article

Already have an account?

Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.