First gold poured at Endeavour's Ity CIL

Upgrade already started to increase nameplate capacity from 4Mtpa to 5Mtpa

This article is 5 years old. Images might not display.

This is the second project Endeavour has brought online ahead of schedule and under budget in the past 18 months, with first gold poured at its flagship Houndé mine in Burkina Faso in October 2017.

As with Houndé, the Ity CIL project was built in under 18 months, with the plant already running at its 4 million tonnes per annum nameplate capacity after a rapid ramp-up.

Ity's first pour yielded around 1,800 ounces of gold, higher than Houndé's first pour of 980oz.

First ore was introduced into the Ity CIL processing plant a month ago, with approximately 135,160 tonnes of ore processed since.

Endeavour said it expected to declare commercial production early in the June quarter, with the start of performance trial testing imminent.

CEO Sébastien de Montessus said the gold pour and fast ramp-up meant the Ity CIL would quickly contribute to Endeavour's cash generation potential.

The company has already started optimisation and de-bottlenecking work to increase the plant nameplate capacity to 5Mtpa at a minimal cost of $10-15 million.

The work includes pipes and pumps upgrades and a second 50t oxygen plant. It doesn't require any additional mining fleet and the upgrades are expected to be completed during scheduled plant maintenance shut-downs throughout the next six months.

"Given its current 15-year mine life and strong exploration potential, our ability to increase the plant size by 1Mtpa to 5Mpta for minimal additional capex represents a very compelling investment and is in line with our focus on capital allocation efficiency and return on capital employed criteria," de Montessus said.

"With this upgrade, Ity has the potential to produce circa 300,000oz of gold per annum at a low AISC."  

Ity's output for 2019 is forecast at 160,000-200,000oz at an all-in sustaining cost of $525-590 per ounce.

Endeavour put the overall project capital expenditure at around $420 million, including the upgrade costs and additional works, such as the construction of a fuel farm, building exploration facilities, and an additional $7 million of crop compensation and resettlement related to prospective exploration grounds.

It is busy with a $11 million exploration programme at the La Plaque target totalling around 71,000m of drilling this year, with the aim of publishing an updated resource in the June quarter and testing other targets, including Floleu, Daapleu SW and Samuel.

 

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.