Two key permits received for Bear Creek's Corani

One permit left, second phase detailed engineering work planned

Staff reporter

This article is 6 years old. Images might not display.

Peru's Ministry of Energy and Mines and the Ministry of Agriculture's Water Authority approved the project's mine construction permit and water availability accreditation, although Bear Creek was still waiting for the separate process plant construction permit.

The company can now build a mine, as well as associated facilities, as well as strip and extract ore according to the Corani mine plan, while being assured there is enough water for the construction and operation of the mine.

The pending process plant construction permit will allow the construction of the Corani processing plant and its associated waste and tailings disposals, water storage system and processing facilities.

Bear Creek CEO Anthony Hawkshaw said the review of the permits by the ministries had been timely and he attributed the company's good relationship with the local communities during the permit approval process to Bear Creek's commitment to supporting them and promoting productive economic activities.

"Our board of directors will consider a Corani construction decision when a compelling project financing structure is arranged. Receipt of these key permits is a major step that will help attract sources of capital," he said.

At the end of 2017, the company was awarded about US$30.4 million after an international tribunal ruled in its favour in an arbitration claim over the expropriation of its Santa Ana project, also in Peru.

It said at the time it would be using the settlement funds to accelerate Corani.

Bear Creek plans to start second phase detailed engineering work soon, which should lead into an engineering, procurement and construction contract.

With the mine plant permit it can also start early works projects, such as building the Corani camp and access road from the camp to the project, while it is busy with the permitting for the construction of an electrical substation and power line in the nearby town of Macusani.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

Mining Journal Intelligence: Investor Sentiment Report 2025

Exclusive insights into the plans, priorities and preferences of 130+ mining investors and top factors influencing investment decisions in 2025.

editions

Mining Journal Intelligence World Risk Report 2024 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 117 jurisdictions globally, assessed across six risk categories and an industrywide survey.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.