PRECIOUS METALS

EIA paves way for Aya to order long-lead construction items for Zgounder

Capacity to expand to 2,700 tonnes per day

Nathan Richardson
EIA paves way for Aya to order long-lead construction items for Zgounder

"This approval, along with our robust expansion feasibility study, announced last week, provides us with enough comfort to order long-lead construction items," Aya's president and CEO, Benoit La Salle, said. 

The expansion of the Canada-based company's flagship mine is planned to lift capacity from 700 tonnes per day to 2,700t/d. 

Based on a silver price of US$22/oz, Aya's expansion feasibility study showed an after tax 5% NPV and after-tax IRR of 48%. The initial mine life is 11 years with an all-in sustaining cost of US$9.58/oz, including sustaining capital expenditures. 

Aya also announced a partnership with the Biotechnology for Sustainable Development in Africa Foundation, which is aimed at developing and supporting local agribusinesses and providing access to international markets in the Askaoun region of Morocco. 

La Salle said the deal highlights the company's commitment to deliver measurable impact to the community, including local-community job creation over the next five years. 

Aya traded on the Toronto Stock Exchange at C$10.13/share on February 28, which was up 4%. The company had a market capitalisation of C$1.06 billion. 

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

Mining Journal Intelligence World Risk Report 2024 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 117 jurisdictions globally, assessed across six risk categories and an industrywide survey.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Journal Intelligence Global Leadership Report 2024: Net Zero

Gain insights into decarbonisation trends and strategies from interviews with 20+ top mining executives and experts plus an industrywide survey.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.